Construction

Construction

Changed traffic conditions and pedestrian access are in place near the site. Russell Street is closed to general traffic between 6:30am to 6:30pm, Monday to Friday and some Saturdays. Please follow signage and instructions. Alternative drop-off locations are available on Grey Street.

Milestones

2023

  • Installation of structural steel and feature precast concrete panels to the front of house sections
  • Commencement of roof sheeting to front of house foyers
  • Progression of services inside the auditorium including electrical, mechanical and hydraulics
  • Works to the back of house and fly tower including electrical and mechanical services, ceiling framing and steelwork
  • Level 8 roof sheeting installed to all three tiers
  • The birdcage scaffolding is completed

2022:

  • Cores reach full height
  • Commencement of the internal structural steel installation
  • Progression of fit-out activity in the lower levels of the building
  • Refurbishment of rehearsal rooms

2021:

  • Installation of two tower cranes to continue major construction
  • Excavation of the orchestra pit
  • Large concrete pours

2020:

  • Lendlease, as Managing Contractor for the project, began exploratory and preparatory work in March 2020 for the new theatre at the Playhouse Green site
  • Construction works begin