Construction

Lendlease, as Managing Contractor for the project, began early preparatory work in early March 2020 for the new theatre at the Playhouse Green site. This included installation of vibration monitoring and service relocation works. 

In April 2020, work began to support the integration of a new theatre into the existing QPAC structure to enable a seamless connection.

Bulk excavation work was undertaken in September 2020, ahead of piling work to support the new theatre’s foundations in October 2020.

From October 2020 until completion of theatre construction, changed traffic conditions and pedestrian access are in place near the site. Lendlease’s construction notices are available here for more information..